Painting Schedule
November 2009 thru December 2012
| Date | Units | Wash Roof | Painting |
| Nov 01-Jan 31-2010 | 15,1-2,3-4 | Yes | |
| Feb. 1-Mar. 31 | 5-6,7-8 | Yes | |
| April 1-30 | 9-10 | Yes | |
| May 1-15 | 18,19-20,21-22-23-24,25-26 | Yes | |
| May 16-Aug 15 | 11,12,13-14,16-17 | Yes | |
| August 15-31 | Vacation/Leave | ||
| Sept 1-Oct 15 | 18,19-20 | Yes | |
| Oct-16-Oct-31 | 27-28,2--30,38-39,37,42 | Yes | |
| Nov 1-Jan 15 2011 | 21,22,23,24,25-26 | Yes | |
| Jan 16-Mar 31 | 27-28,29-30 | Yes | |
| April 1 - April 15 | 35-36,40-41,33-34,31-32 42 | Yes | |
| April 16 - Aug 15 | 38-39,37,42,35-36,40-41,33-34 | Yes | |
| Aug 16 - 31 | Vacation/Leave | ||
| Sept 1 Sept 15 | 51,52-53,54,47-48 | Yes | |
| Sep 16- Dec 31 | 31-32,51,52-53,54 47-48 | Yes | |
| Jan 1- Jan 15 2012 | 49-50,45-46,43-44,15 | Yes | |
| Jan 16 April 30 | 49-50,45-46,43-44 | Yes | |
| May 1- May 15 | 1-2,3-4,5-6,7-8,9-10 | Yes | |
| May 16- May 30 | 11-12,13-14,16-17 | Yes | |
| June 1- Aug 15 | 1-2,3-4,5-6,7-8,9-10 | Yes | |
| Aug 16- Aug 31 | Vacation/Leave | ||
| Sep 1 - Dec 15 2012 | Piggery etc | ||
| Note this schedule is for 35 months |
If you have any queries about this schedule, please contact the Painting Director
To get a copy of this spreadsheet, click here.